After years of delays, the tidal flood control project worth VND10 trillion (US$387 million) is expected to begin operations by the end of November in Ho Chi Minh City, ahead of its planned inauguration in mid-December.

Ho Chi Minh City's $387mn tidal flood control project set to begin operations in late November - Ảnh 1.

Ho Chi Minh City's tidal flood control project is expected to begin integrated system operations in late November. Photo: L.L. / Tuoi Tre

The project's investor, Trung Nam Construction Investment Corporation (Trungnam Group), said it would work with relevant agencies to conduct an integrated operation of the flood control system in late November, in line with instructions from the authorities.

The operation will assess how the project's various components function together before its scheduled inauguration.

Nguyen Tam Thinh, chairman of Trungnam Group, told Tuoi Tre (Youth) online newspaper that the project comprises eight tidal control sluices at Ben Nghe, Tan Thuan, Phu Xuan, Muong Chuoi, Cay Kho, Phu Dinh, Cau Kinh, and Ba Buom.

It also includes about six kilometers of embankments and protective structures, along with 41 smaller sluices at key and flood-prone locations.

The sluice gates are designed to close during high tides to prevent water from entering protected areas and reopen when river levels fall below those inside the system, allowing water to drain while maintaining waterway traffic.

During the rainy season, the system can also regulate and retain water when conditions permit.

To coordinate these operations, the project will integrate 19 monitoring stations with a Supervisory Control and Data Acquisition (SCADA) system, enabling automated control and continuous monitoring.

Once fully operational, the system is expected to help control tidal flooding across approximately 570 square kilometers, benefiting around 6.5 million residents, mainly in central and southern Ho Chi Minh City along the right bank of the Saigon River.

Under the city's new administrative boundaries, the project covers 20 wards and communes in areas formerly belonging to Districts 1, 4, 7, and 8, as well as Nha Be and Binh Chanh Districts.

Ho Chi Minh City's $387mn tidal flood control project set to begin operations in late November - Ảnh 2.

Motorbike riders navigate a flooded street in Ho Chi Minh City. Photo: Supplied

By regulating water levels across rivers and canals, the project is expected to improve rainwater drainage, ease pressure on the city's existing drainage network, and reduce tidal flooding.

It will also help limit saltwater intrusion, improve water quality and the urban landscape, and facilitate inland waterway transport.

Thinh described the project as a "steel shield" that would help Ho Chi Minh City better manage high tides, protect urban infrastructure, and reduce the long-term impact of rising water levels.

Nearly a decade of construction and delays

Officially known as the Ho Chi Minh City Tidal Flood Control Project with Climate Change Considerations (Phase 1), the project began construction in 2016 under a build-transfer (BT) contract.

By November 2020, more than 90 percent of the work had been completed, but construction was suspended due to legal obstacles and unresolved land payment procedures for the investor.

After years of delays, the payment issues were resolved, allowing work to resume in early February 2026.

The project is now approaching its first integrated operation, with an official inauguration planned for mid-December.