A modern machine welds rails for Phu Quoc’s urban railway, completing each joint in just three to four minutes. Photo: Chi Cong / Tuoi Tre
Engineers and workers are working around the clock at the construction site in Phu Quoc Special Zone, An Giang Province to meet the project deadline for APEC 2027.
Construction teams are working across multiple sections to install and align rails, tighten bolts, and weld rail sections using the 33-tonne machine.
Engineers monitor each welding operation to ensure the joints meet technical requirements and allow trains to run smoothly and safely.
Nguyen Huy Thanh, a representative of the rail-welding contractor, said the company had deployed a mobile automatic rail-welding machine for the first time on the Phu Quoc urban railway project.
He said the deployment marked progress in technology adoption and the ability of Vietnamese workers to operate advanced equipment.
Under favorable site conditions, the machine takes three to four minutes to complete one rail joint.
It can weld 250-300 meters of single rail per day, equivalent to more than 20 joints.
Its productivity is three to four times that of the aluminothermic welding method.
"The machine uses electric flash-butt welding technology. The two ends of the rail sections are heated and pressed together using a specialized system, with technical parameters adjusted to suit each type of rail," Thanh said.
Engineers then use a grinding machine to smooth the welded joints to meet technical and aesthetic requirements, he added.

The rail-welding machine produces smooth and strong joints. Photo: Chi Cong / Tuoi Tre

An engineer operates the machine to weld rail joints on Phu Quoc’s urban railway. Photo: Chi Cong / Tuoi Tre

The rail-welding machine uses electric flash-butt welding technology. Photo: Chi Cong / Tuoi Tre
According to Sun Group, one of Vietnam's leading real estate developers, the contractor has mobilized around 1,300 engineers and workers across seven construction fronts on the project.
More than 11 kilometers of track has been installed to date, while all bored piles for the bridge and tunnel sections have been completed.
The contractor has also completed the reinforced concrete structures of the tunnel sections connecting DT.975 Road to Phu Quoc International Airport.
Rail installation in these sections is scheduled to begin next.
The nearly-18-kilometer urban railway will have six stations featuring Vietnamese cultural elements.
The project has a total investment of around VND9 trillion (US$344 million).
The railway is being built to serve APEC 2027 and improve transport infrastructure on Phu Quoc Island.

An engineer operates the control panel to position the machine for rail welding. Photo: Chi Cong / Tuoi Tre

The rail-welding process produces bright sparks and intense heat. Photo: Chi Cong / Tuoi Tre

After the machine completes each weld, skilled engineers grind the joints smooth to meet the project's technical and aesthetic requirements. Photo: Chi Cong / Tuoi Tre

Engineers and workers are divided into teams to align and install rails for Phu Quoc’s urban railway. Photo: Chi Cong / Tuoi Tre
Phu Quoc is set to host the APEC Economic Leaders' Meeting in November 2027, following previous editions held in Da Nang in 2017 and Hanoi in 2006.
The high-profile international event is expected to accelerate infrastructure development, attract investment, and provide fresh momentum for the island's tourism and real estate sectors.
The Ky - Chi Cong / Tuoi Tre News