Tidal waters continued to rise across the city as part of the regular tidal cycle on Tuesday afternoon.
At the Tan Thuan tidal control sluice, water levels on either side of the structure differed as its gate was closed.
Along Tran Xuan Soan Street, one of the areas regularly affected by tidal flooding, the road remained free of inundation while the gate was being closed for testing.
Tran Ngoc Ly, who runs a business along the street, said she was encouraged by the changes seen over the past two days since the Tan Thuan sluice began trial operations.
During previous high-tide periods, water spilled onto the street, disrupting traffic and affecting businesses along Te Canal, she said.


A comparison of Tran Xuan Soan Street, which remained dry on November 24, 2026 (left), and its previous condition, when it was frequently flooded. Photos: Tri Duc - Chau Tuan / Tuoi Tre
"Whenever the street was flooded, many people chose alternative routes to get home, and fewer customers stopped by to shop,” she shared.
“This afternoon, however, I watched the water level rise near the drainage outlets, but it had not yet spilled onto the road.”
She expressed hope that the facility would operate reliably and deliver lasting improvements, making daily life and business easier for her and other local residents.

Tran Ngoc Ly expresses delight at the improvements along Tran Xuan Soan Street over the past two days since the Tan Thuan tidal control sluice began trial operations. Photo: Tri Duc / Tuoi Tre
At the intersection of Nguyen Huu Tho and Nguyen Thi Thap Streets in Tan Hung Ward, the street surface was also relatively dry, with no visible signs of tidal flooding.
Thanh Son, a ride-hailing driver who regularly travels through the area, said he was surprised to find the roads dry during the current high-tide period.
"Back in late October, traffic here became extremely difficult whenever the tide rose,” he said.
“During rush hour, vehicles would line up bumper to bumper, splashing water everywhere.
“I'm really pleased that the road is no longer flooded.
“Getting around for work is much easier now.”


Traffic flows smoothly along Nguyen Thi Thap Street in Tan Hung Ward, with no prolonged congestion like that experienced during the late-October high-tide period. Photos: Dang Linh / Tuoi Tre
Meanwhile, at the Phu Dinh sluice, residents began gathering at around 4:00 pm to watch the trial closure of the gate.
Many expressed hope that the project would soon be put into effective operation, easing their longstanding concerns about flooding whenever tidal waters rise.
Pham Minh Phuong, 48, a resident of An Lac Ward, said his neighborhood normally experienced flooding around the full-moon period, when tides tend to rise significantly.
However, with the streets remaining dry on Tuesday, he decided to visit the Phu Dinh sluice to see the testing.
"Although this is still only a trial, I feel quite reassured because the project is already showing visible results,” he said.
“Normally, the tide would be rising onto the streets in my neighborhood at this time, but today everything is dry.”

The gate of the Phu Dinh tidal control sluice is closed at around 4:00 pm, November 24, 2026. Photo: Ngoc Lan / Tuoi Tre
Le Ngoc Thanh, 56, who has lived along Phu Dinh Street for around 10 years, also welcomed the improvements.
"Residents are very happy. The streets are clean and getting around is much more comfortable,” he said.
“However, there are still some problems with certain manhole covers, where a little tidal water continues to seep through.
“I hope the relevant units will carry out maintenance and fix these issues soon.”

Residents living along Phu Dinh Street, near the tidal control sluice, gather out of curiosity to watch the facility ahead of the project's official launch. Photo: Ngoc Lan / Tuoi Tre

The Cay Kho tidal control sluice also closes its gate on the afternoon of November 24, 2026. Photo: T.N.
At 11:55 am on Wednesday, Trung Nam Construction Investment Corporation (Trungnam Group), the investor behind the city’s flood control project, operated all project components in an integrated system for the first time, marking the project's official commencement of operations.