Standing Deputy Prime Minister Pham Gia Tuc chairs the meeting. Photo: Phuong Nguyen / Tuoi Tre
Standing Deputy Prime Minister Pham Gia Tuc chaired a meeting on Wednesday to address obstacles and accelerate the project in Dong Nai City.
Airports Corporation of Vietnam (ACV), the project investor, said it could not complete component project 3 in 2026 as scheduled due to objective and subjective factors.
Major packages, including the passenger terminal, cargo terminal No. 1, parking facility and airport management systems, are expected to be completed or finish trial runs in June.
ACV reported three main groups of problems affecting component project 3.
Frist, some materials and equipment differ from contract specifications in manufacturer, brand, type and origin.
Orders, deliveries and installation took place before the investor approved the changes and contract amendments were signed.
Second, some completed works were built and accepted based on construction drawings that do not match the approved technical design.
Corresponding technical design adjustments have not been made.
Third, other construction work began before construction drawing documents were approved.
ACV said resolving these issues was necessary for construction acceptance and approval to put the airport into operation.

ACV Acting General Director Nguyen Duc Hung delivers a report. Photo: Phuong Nguyen / Tuoi Tre
The corporation proposed that the government assign the Ministry of Construction to review the progress of all component projects and submit a proposal to extend phase 1 implementation to 2027-28.
Vietnam Air Traffic Management Corporation said some remaining work under component project 2 depended on infrastructure completion under component project 3.
It proposed prioritizing technical facilities and infrastructure connections to ensure air traffic management systems could be deployed.
Vietnam Airlines and Vietjet said they were preparing to operate at Long Thanh in line with approved plans.
They warned that simultaneous construction and operations could pose risks to safety and service quality.
Vietnam Airlines said airlines needed sufficient preparation time, particularly for international flights, as passengers often book tickets months in advance.
Ho Chi Minh City and Dong Nai City authorities said they had established task forces and drawn up traffic plans for routes connecting to the airport.
Standing Deputy Prime Minister Pham Gia Tuc ordered relevant agencies to resolve project obstacles and address existing problems without legitimizing violations or allowing new ones.
Investors, ministries, agencies and local authorities must handle issues within their authority and submit matters beyond their jurisdiction to higher-level authorities.
ACV bears full responsibility to the government and prime minister for the progress and quality of component project 3 and its construction packages.
ACV must also review payment issues and resolve them in line with regulations to ensure contractors have sufficient funding to continue work.
The corporation must also assess the quality and suitability of materials and equipment facing problems.
The Ministry of Construction will monitor and inspect project progress and guide ACV on investment management and construction quality control.
ACV must review all remaining work under component project 3 and set deadlines for construction, equipment installation, trial runs, operational testing and the earliest possible opening date.
As the project cannot meet the 2026 deadline approved by the National Assembly, ACV must report to the government and send its report to the Ministry of Construction within a week of the meeting.
The ministry must submit a progress report to the government before December 10 for submission to competent authorities to consider adjustments to the investment policy.
ACV must also devise dust-control measures and ensure phase 1 operational safety while phase 2 is under construction.
He added that the airport could only open after meeting all required conditions and ensuring absolute safety.
The Ministry of Construction said Long Thanh's operational capacity depended on both airport infrastructure and transport connections.
Access routes must accommodate peak-hour passenger traffic, with high-quality public transport, parking facilities and transfer arrangements between Tan Son Nhat and Long Thanh airports.
These factors will also affect airlines' flight schedules and route planning.
Travel from Ho Chi Minh City to Long Thanh currently relies entirely on roads.
Several expressway sections and the An Phu interchange remain under construction and are expected to be largely completed in early Q2-2027.
Transport capacity and traffic arrangements cannot yet be fully assessed.
Passengers have raised concerns about travel times, congestion and the risk of missing flights, particularly when transferring between the two airports.
The ministry said convenient travel could not be guaranteed from the outset if access routes were not fully connected when Long Thanh begins operations.
It urged local authorities and Vietnam Expressway Corporation (VEC) to accelerate construction and prepare contingency plans for traffic disruptions and demand exceeding road capacity.
The Ky - Hong Quang - Cong Trung / Tuoi Tre News