Cleared land must be handed over to Long Thanh airport project in Q1

Must read

Long Thanh airport construction 76% complete

Long Thanh airport construction 76% complete

podcast June 22, 2026

Construction of Long Thanh International Airport’s Component 3 has reached nearly 76% of the value of signed contracts, with more than 7,300 workers deployed under a 180-day acceleration campaign, according to the Airports Corporation of Vietnam (ACV).

HCMC – Deputy Prime Minister Tran Hong Ha has told Dong Nai Province and the Airports Corporation of Vietnam (ACV) to expedite the clearing of the remaining areas to deliver all sites of the first phase of the Long Thanh International Airport project this quarter.

Latest articles

Long Thanh airport construction 76% complete

Long Thanh airport construction 76% complete

podcast June 22, 2026

Construction of Long Thanh International Airport’s Component 3 has reached nearly 76% of the value of signed contracts, with more than 7,300 workers deployed under a 180-day acceleration campaign, according to the Airports Corporation of Vietnam (ACV).