Cost of Ring Road No. 3 section up by over VND1.6 trillion

Must read

Long Thanh airport construction 76% complete

Long Thanh airport construction 76% complete

podcast June 22, 2026

Construction of Long Thanh International Airport’s Component 3 has reached nearly 76% of the value of signed contracts, with more than 7,300 workers deployed under a 180-day acceleration campaign, according to the Airports Corporation of Vietnam (ACV).

The estimated cost of the Tan Van-Nhon Trach section of the Ring Road No. 3 project, which will connect HCMC, Binh Duong, Dong Nai and Long An, has risen by over VND1.6 trillion after six years of delays.