Vietnam's largest airport Long Thanh is set to begin commercial operations on December 24, 2026. Photo: Tuoi Tre
Priority will be given to domestic routes and short-haul international services.
The Standing Committee of the Dong Nai Party Committee on Thursday held a working session with Airports Corporation of Vietnam (ACV) to review preparations for the airport's opening.
Airport operations to be carried out in three phases
The massive airport will see its operations gradually scaled up over three phases.
The first phase will run from December 24, 2026 through the end of March 2027, while the second phase will take place from April to October 2027.
The third phase will begin in October 2027.
During the initial phase, ACV will put the western wing and central section of passenger terminal T1 into operation.
The airport is expected to handle some 6-10 percent of its designed capacity, equivalent to 20-30 flights per day.
Domestic routes and short-haul international services registered by airlines will be prioritized during the period.
At the meeting, ACV also outlined key areas requiring coordination with Dong Nai authorities to ensure the airport can begin operations smoothly.
These include external transport links and passenger transportation, aviation security and safety, fire prevention and firefighting, search and rescue, obstacle limitation and airspace management, as well as healthcare, disease prevention and quarantine services.
Regarding transport connectivity, the Dong Nai People's Committee said construction of component subproject 1 of the Bien Hoa-Vung Tau Expressway project and component subproject 3 of the Ho Chi Minh City Ring Road No. 3 project was being accelerated, with completion targeted for December.
Some road projects are also expected to be completed in time to open alongside Long Thanh International Airport.
Meanwhile, the Dong Nai Department of Construction has issued a plan to ensure coordinated connections with expressways and organize traffic flows serving the airport.

Officials from Dong Nai City, where Long Thanh International Airport is located, hold a meeting with Airports Corporation of Vietnam (ACV) to review preparations for the airport's opening, November 19, 2026. Photo: A Loc / Tuoi Tre
Urgent comprehensive review of airport transport connections
Speaking at the meeting, Vo Tan Duc, deputy secretary of the Dong Nai Party Committee, stressed that the airport project was entering a decisive stage, with the first phase targeted to become operational in December.
He noted that the remaining time was limited, while the volume of work was substantial.
Therefore, the challenge was not simply to complete construction works but also to ensure that all necessary conditions were fully and synchronously prepared so the airport could operate safely, smoothly and efficiently.
He asked ACV to provide a detailed report on the airport's operational readiness, together with plans for its management and operation.
On transport connectivity, he called on the municipal Department of Construction to work with ACV and relevant agencies to conduct a comprehensive review of the entire road network serving the mammoth airport.

A road inking to Long Thanh International Airport. Photo: A Loc / Tuoi Tre
Vietnam Airlines, Vietjet register hundreds of flights per week
Based on slot allocation data from the Civil Aviation Authority of Vietnam and airlines' official operating plans, ACV estimates that Long Thanh International Airport will handle a maximum of 226 flights per week between December 2026 and March 27, 2027.
Of this total, 44 flights will be international services and 182 will be domestic flights.
Vietnam Airlines has registered international services connecting Long Thanh with Beijing, Guangzhou, Hong Kong, and Manila, with a combined frequency of 44 flights per week.
For domestic operations, the airline plans to launch 28 weekly flights on the Long Thanh-Hanoi route.
Meanwhile, Vietjet Air has registered up to 154 flights per week across five domestic routes linking Long Thanh with Hanoi, Hai Phong, Vinh, Thanh Hoa and Da Nang.
According to ACV, the official flight schedule will be updated in consultation with airlines during the first week of December.
Long Thanh International Airport spans about 5,000 hectares, with a total estimated investment of more than VND336.63 trillion (US$13 billion).
Construction began in 2020.
Once fully completed, the airport will have a total capacity of up to 100 million passengers and five million metric tons of cargo per year.