A view of Chan May Port in Chan May–Lang Co Commune, Hue City, central Vietnam. Photo: Supplied
Deputy chairman Phan Quy Phuong signed a decision approving Chan May Infrastructure Development Joint Stock Company as the project investor.
Of the total VND1.452-trillion investment, about VND217.8 billion ($8.3 million), or 15 percent, will be contributed by the investor and about VND1.234 trillion ($47.1 million), or 85 percent, will be mobilized from other sources.
Compensation, site clearance, and land handover are scheduled for the first quarter of 2026 to the fourth quarter of 2027.
Construction must begin within three months of land lease and handover procedures being completed, expected in the fourth quarter of 2026.
The project is to be completed within 24 months of land handover, around the fourth quarter of 2028, the committee said.
Bao Anh - Nhat Linh / Tuoi Tre News