Ho Chi Minh City has officially issued a decision exempting private houses, temporary structures, electric vehicle (EV) charging stations and battery-swapping cabinets from construction permits, effective November 30.

Ho Chi Minh City exempts private homes, temporary structures, EV charging stations from construction permits

Construction projects exempt from permits must still comply with regulations on planning, land use, fire safety, environmental protection and acceptance procedures. Photo: Thuan Van / Tuoi Tre

Hoang Nguyen Dinh, vice-chairman of the Ho Chi Minh City People's Committee, has signed a decision on construction permit exemptions for projects across the city.

Under the decision, in addition to projects already exempted under the Law on Construction, private houses owned by households, individuals or organizations in the city will also be exempt from construction permits if they are fewer than seven stories tall above ground level, have a total floor area of less than 500 square meters, and are located in areas covered by an approved urban architectural management regulation, a 1:500 detailed plan or a separate urban design.

Commune- and ward-level authorities, special administrative zones and the Department of Construction will issue construction permits within their respective jurisdictions for such houses if investors request them.

Temporary structures will also be exempt from construction permits.

The municipal People's Committee will determine the criteria, conditions, permitted duration, management, operation, dismantling, relocation and site restoration requirements, as well as other regulations governing such structures.

Charging poles and battery-swapping cabinets installed on non-agricultural land or land managed by the state will also be exempt from construction permits, except for land used for national defense and security purposes.

Investors and relevant parties must ensure that the installation of these facilities complies with current technical regulations and standards.

Ho Chi Minh City exempts private homes, temporary structures, EV charging stations from construction permits - Ảnh 1.

Electric vehicle charging stations are among the facilities exempt from construction permits in Ho Chi Minh City. Photo: Tri Duc / Tuoi Tre

Compliance with planning, fire safety, environmental regulations

To manage construction activities involving projects exempt from permits, the Department of Construction must provide guidance to commune- and ward-level authorities, special administrative zones and relevant organizations and individuals.

The department must also issue guidelines on construction order management and oversee the receipt of construction commencement notices, construction order management and acceptance procedures.

The Department of Planning and Architecture must coordinate with commune- and ward-level authorities and special administrative zones to review approved zoning plans, detailed plans and the city's urban architectural management regulations, and update them on the city's planning website to facilitate public access.

It must also guide local authorities on approving plans and determining road reserve boundaries, building lines and permitted building heights.

Commune- and ward-level authorities and special administrative zones must make planning documents and architectural management regulations publicly available as a basis for granting construction permit exemptions.

Ho Chi Minh City exempts private homes, temporary structures, EV charging stations from construction permits - Ảnh 2.

Investors must submit construction commencement notices to the commune-level People's Committee where their projects are located. Photo: Ai Nhan / Tuoi Tre

Investors must check planning information, including permitted building heights, road reserve boundaries, architectural indicators and design requirements, to ensure full compliance with regulations on land use, planning, architecture, fire prevention and fighting, and other relevant matters.

They must also submit construction commencement notices to the commune-level authorities.

If a construction project spans the territories of two commune-level administrative units, the investor must submit commencement notices to both authorities.

Design and supervision contractors must fulfill their respective responsibilities for construction quality and project execution in accordance with their professional functions.

Compliance with construction regulations, acceptance procedures

Under the decision, projects exempt from construction permits must still fully comply with legal requirements on land use, planning, architecture, fire prevention and fighting, environmental protection, traffic, and the management and protection of technical infrastructure facilities, as well as other relevant regulations.

Construction order management, project acceptance and the issuance of ownership certificates for such projects must follow current laws.

Thanh Ha - Ai Nhan / Tuoi Tre News